Helping to minimise the impact of construction
The submission of the Construction Management Plan (CMP) to help minimise the impact of construction
Steps to submitting a CMP:
You must account for timescales of CMPs in construction programmes and contracts.
- prepare your CMP: Construction Management Plan (CMP) pro-forma (Word)
- statement and Checklist for: Cumulative Impact Areas in Cental London (Editable -PDF)
- read the community liaison guidance (PDF) and construction working group for developers and Contractors (PDF)
- read the Camden Minimum Requirements (PDF)
- read the Guide for Contractors Working in Camden (PDF)
- advice note the CMP Implementation Fee and Bonds
- submit your CMP to: [email protected].
Note: It can take around six to twelve weeks or more to approve the CMP, depending on the nature of the development and the number of revisions submitted.